How to run a subcontractor tender in construction

A step-by-step subcontractor tender process for builders: trade packages, addenda to every tenderer, comparable bids, award and the tender record.

A subcontractor tender asks several trades to price the same package, on the same documents, by the same date, so you can compare like with like and award with confidence. Most tender problems come from the same few gaps: tenderers pricing different revisions, addenda that do not reach everyone, and bids that cannot be compared. Here is a process that closes them.

The tender process, step by step

  • 1. Build the trade package: scope of works, the current drawings and specification, the programme, contract conditions and the pricing schedule you want returned.
  • 2. Choose the tenderers: usually three or more per package, checked for licences, insurance and capacity before they are invited.
  • 3. Invite and set the rules: one closing date and time, how questions are asked, and how bids are returned.
  • 4. Answer questions fairly: when one tenderer asks something that changes the price, send the answer to everyone.
  • 5. Issue addenda to every tenderer: each change to the documents goes out as a numbered addendum to all tenderers at once, and each bid confirms which addenda it includes.
  • 6. Close and compare: compare bids side by side against the same scope, and list each tenderer’s exclusions and qualifications.
  • 7. Clarify and award: close out scope gaps in writing, award, and let the unsuccessful tenderers know.
  • 8. Carry it into delivery: the awarded scope, documents and correspondence become the start of the subcontract record.

What makes bids comparable

CheckWhy it matters
Same document revisionsA bid priced on an old drawing is not the same price
All addenda acknowledgedShows each tenderer priced every change
Same pricing scheduleLets you compare item by item, not just the total
Exclusions listedThe cheapest bid often excludes the most
Qualifications in writingAnything agreed in a phone call is lost at award

Keep the tender record

Who was invited, what they received, which addenda went out and when, every question and answer, and why the award was made. On government and larger private work you may be asked to show the process was fair. Standards Australia’s AS 4120, the Australian code of tendering, sets out the principles many builders follow.

How Commnia runs tenders

  • Send trade packages with the current documents from the Document Register, so every tenderer prices the same revisions.
  • Issue addenda to every tenderer at once, with every send logged.
  • Bidders reply without logging in, so subcontractors do not need an account to tender.
  • Compare bids side by side and award.
  • Carry the award into delivery: the awarded subcontractor carries straight into the project, with the documents and correspondence already in one record.

Common questions

How many subcontractors should we invite to tender?

Three is a common minimum for a trade package, so you have a real comparison. Inviting many more adds work for everyone and rarely improves the result.

Should a late tender be accepted?

Set the rule in the invitation and apply it the same way to everyone. Accepting one late bid and not another is the quickest way to a dispute.

What is an addendum in a tender?

A formal change to the tender documents issued before closing, such as a revised drawing or an answer to a question. It goes to every tenderer and each bid should confirm it was included.

This article is general information, not legal advice. Checked October 2026.