ITP Template for Construction: How to Run Inspections on Site

An inspection and test plan (ITP) lists every check a piece of work has to pass, who checks it, what it is checked against and the record that proves it. Done well, it is the backbone of your quality record at handover. Done on paper, it is usually the first thing to go missing.
What an ITP is for
An ITP turns the drawings and specification into a list of checks for one activity, such as a slab pour, waterproofing or a fire-rated wall. It tells the site team what to look at before work moves on, and it gives the builder, superintendent and certifier one record of what was checked, by whom and when.
Many head contracts and most government projects ask for a quality plan with ITPs for key activities. Even where it is not required, a complete set of ITPs is the quickest way to answer a defect claim years later.
What every ITP should include
| Column | What goes in it |
|---|---|
| Activity or stage | The step being checked, in the order work happens |
| What is checked | The specific item: set-out, cover, fixings, membrane laps |
| Acceptance criteria | The drawing, specification clause or Australian Standard it must meet |
| Who checks | Trade, site manager, engineer or certifier |
| Type of check | Visual, measurement, test result, photo, or a stage someone must sign before work continues |
| Record | Signature, date, photos, test certificate |
A simple ITP template you can copy: concrete slab
| Stage | Check | Criteria | Who | Record |
|---|---|---|---|---|
| 1. Formwork | Levels, set-out, edge form | Structural drawings | Site manager | Signed, photo |
| 2. Reinforcement | Bar size, spacing, laps | Structural drawings | Engineer | Signed, photos |
| 3. Cover | Chairs and cover to reinforcement | Specification | Site manager | Measurements, photo |
| 4. Embedments | Penetrations, conduits, cast-ins | Services drawings | Trades | Signed |
| 5. Pre-pour sign-off | All stages above complete | This ITP | Site manager, engineer | Signed |
| 6. Pour and cure | Slump, curing method | Specification | Concreter | Docket, photos |
| 7. Test results | Cylinder strengths | Specification | Lab | Test certificate |
Hold points and witness points
Two terms appear in most ITPs. A hold point is a stage where work must stop until a nominated person signs it off, such as the pre-pour sign-off above. A witness point is a stage where that person must be told in time to attend, but work can continue if they choose not to. Mark both clearly, because they are where disputes start when they are missed.
Running ITPs on site without the paper chase
- One ITP per area. Open it per level, unit or lot, so you can see at a glance which areas are complete.
- Record at the time of the check. Photos and signatures taken later rarely match what was there.
- Turn every failure into a defect straight away. A failed check that lives only on the ITP gets forgotten.
- Review by location every week. Look for areas with open ITPs before the next trade covers the work.
- Keep the records for the long term. Builders are commonly exposed to defect claims for years after completion, so keep ITPs with the project record.
How Commnia runs ITPs
- Build your own ITPs in SmartForms with drag and drop, and change them yourself whenever the specification changes.
- Required steps cannot be skipped, and each check carries its photos, location and signature.
- Several people can complete the same ITP, so trades, site manager and engineer each sign their part.
- A failed check raises a defect with the ITP attached, ready to assign to the trade.
- The Forms Dashboard shows every ITP as New, Active, Approval or Completed, grouped by location, trade or company.
- Works offline on iPhone and Android and syncs when signal returns. Results export to Excel.
Common questions
Who writes the ITP?
Usually the builder for its own work, and each subcontractor for its scope, reviewed by the builder. Your contract may also require the superintendent or principal to review ITPs before work starts.
Is an ITP a legal requirement?
Not on every project. It is most often a contract requirement, especially on government and larger commercial work. Check the quality clauses of your contract and your state’s inspection requirements.
What is the difference between an ITP and a checklist?
A checklist lists items to tick. An ITP adds the acceptance criteria, who is responsible and the record each check needs, so it stands up as evidence later.