How to write an extension of time (EOT) claim in construction

An extension of time (EOT) claim asks for more time to reach practical completion because of a delay the contract says you are entitled to time for. To succeed, it must be made on time, in the form the contract requires, and show the cause, the delay to the critical path, your entitlement under the contract, the evidence and the number of days claimed. Here is how to put one together, and why claims fail.
The parts of an EOT claim
| Part | What it must show |
|---|---|
| Notice | That you notified the delay, and then claimed, within the time limits and in the form the contract sets |
| Cause | What happened, when it started and, if it has ended, when it ended |
| Delay to the critical path | That the event actually delayed work needed to reach practical completion, not just some work |
| Entitlement | The contract clause that gives time for this cause, and that any conditions in it are met |
| Evidence | Records made at the time that prove the cause and its effect |
| Quantum of time | How many days you claim, and how you calculated them |
Step by step
- Read the contract first. Find the EOT clause, the notice requirements, who the notice goes to, the qualifying causes of delay and any time bars. Check the special conditions, because standard clauses are often amended.
- Give notice as soon as you know of a likely delay. Do not wait until the delay is over or the effect is fully known. A short notice now can be followed by a detailed claim.
- Record the delay while it happens. Site diary entries, photos, correspondence, RFIs and instructions made at the time are worth far more than a reconstruction later.
- Show the effect on the program. Compare the current program before and after the event and show how the critical path moved. Explain any float used.
- Link the cause to the contract. Quote the clause that gives you time for this cause, and show each of its conditions is met.
- Calculate the days. Claim working days or calendar days as the contract defines them, and account for any days lost to causes that do not qualify.
- Submit in the required form. Use the address, method and format the contract sets, and keep proof of when it was received.
- Update the claim if the delay continues, as the contract requires, and keep records of every response.
Why EOT claims fail
- Late notice: many contracts make notice within a set time a condition of entitlement. Courts have applied these time bars strictly, for example in CMA Assets v John Holland (Supreme Court of WA, 2015), where claims were found to be out of time.
- No evidence: a claim built from memory after the event is easy to reject. Records made at the time carry weight.
- No critical path delay: the event delayed some work, but not completion.
- Concurrent delay: if your own delay overlapped with the delay you claim for, the contract may reduce or remove your entitlement. Read how your contract deals with it.
- Wrong form or wrong person: sent to the site manager instead of the superintendent, or by a method the contract does not allow.
- Not a qualifying cause: the contract does not give time for that cause, or the risk was allocated to you.
NSW, VIC and QLD
There is no single EOT statute in NSW, Victoria or Queensland. Your right to time, the notice periods and the time bars come mainly from the contract you signed, so two jobs in the same state can have very different rules. Standard forms such as AS 4000 set time limits for notifying delays and claiming extensions, and principals often amend them to be shorter or stricter. Read your own contract, including the special conditions, rather than relying on a general rule.
How Commnia helps
- EOT claims in the project record: raise extension of time claims and RFIs in Commnia, so the claim and what led to it sit in one place.
- Approved from the email: the approver can approve or reject the claim straight from the Commnia EOT email.
- An EOT register: report every EOT sent, approved and rejected, the total days, and the new completion date, which moves forward on each approval, excluding RDOs and public holidays.
- Correspondence filed from Outlook: project email is filed into the project, so notices and replies are not stuck in one person’s inbox.
- Documents and transmittals: the Document Register holds all file types, and every transmittal send is logged, so you can show what was issued and when.
- Daily records: sign-ons flow into the Site Diary with labour by company, and the day’s weather is added automatically, giving you a dated record of who was on site and the conditions.
Common questions
What is an extension of time in construction?
It is an adjustment to the date for practical completion, granted under the contract for a delay the contractor is entitled to time for. It usually protects the contractor from liquidated damages for that period.
Does an extension of time mean I get paid for the delay?
Not automatically. Time and money are usually dealt with separately. Whether you can claim delay costs depends on the contract and the cause.
What if I missed the notice deadline?
Submit the notice and claim as soon as possible anyway, and get legal advice. Some contracts give the superintendent power to extend time even without a valid claim, but you cannot rely on it.
Is wet weather a valid reason for an EOT?
Only if your contract says so. Many contracts allow time for inclement weather beyond an allowance, and others exclude it. Keep daily weather and site records either way.
What evidence supports an EOT claim?
Site diaries, photos, correspondence, RFIs and their answers, instructions, transmittals showing when information arrived, and programs before and after the delay.