What poor document and correspondence control really costs a builder

Poor document and correspondence control costs a builder in four ways: rework built from the wrong revision, claims lost because the notice cannot be found, time spent searching, and exposure to defect claims after handover. None of it shows up as a line in the budget, which is why it keeps happening.
1. Rework from the wrong revision
A trade builds from a drawing that was superseded last week, and the work comes out. Australian research has measured it. A 2018 study of one Australian builder’s own records, covering 19,605 rework events across 346 projects, found rework averaged 0.39% of contract value, and that it cut the company’s average yearly profit by 28% (Love and others, 2018). Earlier Australian research found errors and omissions in contract documents among the main causes (Love and Edwards, 2005). On a job with a $1 million margin, 28% is $280,000.
2. Claims lost on paperwork
Most head contracts, including AS 4000, set strict time limits and formats for notices of delay, extensions of time and variations. A claim that is valid on the facts can still fail because the notice went late, went to the wrong person, or cannot be shown to have been sent. The same applies to the instructions and RFI answers that prove a variation was directed.
3. Time spent searching
When project email lives in personal inboxes and drawings live in shared folders, every question starts with a search: which revision went to the subcontractor, who approved the change, where the consultant’s answer is. Multiply that by every person on every project, every week.
4. Exposure after handover
Defect claims can arrive years after completion. If the drawings, transmittals, inspections and correspondence from the job are scattered or gone when staff leave, the builder cannot show what was approved and built.
Where the cost comes from, and the control that stops it
| Gap | Control |
|---|---|
| Nobody is sure which revision is current | One drawing and document register, with the current revision obvious to everyone |
| No proof of what was sent to whom | Transmittals for every issue, with each send recorded |
| Project email in personal inboxes | Correspondence filed to the project, where the whole team can find it |
| Notices sent late or informally | A register of RFIs, notices and claims, with dates and responses |
| Records lost when people or systems change | One project record, kept after handover |
For a step-by-step procedure, see construction document control: a practical procedure.
How Commnia closes the gaps
- Document Register: every file type, with overlay compare to see what changed between revisions.
- Transmittals: documents go out by transmittal, with every send logged.
- Project email from Outlook: file project email to the project, so correspondence is shared, not stuck in one inbox.
- RFIs and extension of time claims: raised, answered and tracked in the same project record.
- Aftercare: keeps the project record available after handover.
Common questions
How much does rework cost on a construction project?
A 2018 study of 346 projects from one Australian builder’s records found rework averaged 0.39% of contract value, which cut the builder’s yearly profit by 28%. Small percentages matter because margins are thin, and errors in contract documents are one of the main causes.
Is a shared drive enough for document control?
It stores files, but it does not show which revision is current, record what was sent to whom, or keep project email with the documents. Those gaps are where the cost comes from.
How long should a builder keep project records?
At least as long as the builder can be exposed to claims, which for building defects can run for years after completion. Check your contracts and your state’s building laws.
Sources: Love, P.E.D., Smith, J., Ackermann, F., Irani, Z. and Teo, P. (2018), “The costs of rework: insights from construction and opportunities for learning”, Production Planning and Control. Love, P.E.D. and Edwards, D.J. (2005), “Calculating total rework costs in Australian construction projects”, Civil Engineering and Environmental Systems. This article is general information, not legal advice. Checked October 2026.